Main Street road work begins July 8 in Logan

LOGAN – If you drive on Main Street in Logan during the overnight hours, expect some major delays beginning Monday, July 8.

A pavement rehabilitation project is set to get underway from the Y-Intersection to 1000 North, according to the Utah Department of Transportation (UDOT).

Construction crews will be removing and replacing the top layer of asphalt on Main Street during mostly night-time hours and weather permitting.

Work hours on weeknights are scheduled from 8:30 p.m. – 7 a.m.

Saturday and Sunday hours are 8:30 p.m. – 10 a.m.

What to expect:

  • There will be lane shifts and restrictions during work hours throughout the duration of the project.
  • Motorists should expect delays and are advised to use alternate routes.
  • Business and residential access will be maintained. Brief driveway closures are possible when equipment is passing by residential and business accesses during milling and paving operations.
  • Parking on Main Street will not be permitted during work hours.
  • Noise and lighting impacts should be expected in residential areas at night.

Tentative work schedule:

  • July 8-14: Lower utility manholes below the pavement surface to prepare for resurfacing
  • July 15-early August: Rotomill and repave Main Street.
  • July 23-24: Construction will be suspended for Pioneer Day.
  • Early – mid August: Raise utility manholes back to roadway surface grade and place pavement markings and messages.
  • Mid- late August: Final clean-up and project completion.

Free News Delivery by Email

Would you like to have the day's news stories delivered right to your inbox every evening? Enter your email below to start!

Leave a Reply

Your email address will not be published. Required fields are marked *

This site uses Akismet to reduce spam. Learn how your comment data is processed.